TAP News November 2007

1. Project Overview

Despite a number of negative reports in the press, TAP has remained largely silent since issuing its Status Report in January 2007. The reason for this is that the proposal is unchanged and that the scheme remains the same as that declared in January. i.e.

The TAP team of 4 volunteers has continued to investigate all aspects of the proposal (environmental issues, archaeological issues, planning consent requirements, Environment Agency requirements, landowner consents, National Grid connections, professional assistance, implementation costs, funding opportunities and potential benefits). This process has taken far longer than anticipated but has now reached a point of clarity.

The good news is that the proposal:-

Funding has been received to enable the "Pre-Project" phase to be completed. This phase is primarily to achieve all the necessary permissions to allow the project to proceed. (i.e. Planning consent, Environment Agency consent, CADW consent, landowner consent). It also covers the design spec, flow measurement, confirmation of expected performance, and a full project cost estimate for subsequent funding purposes. This is a lengthy process and will take until Spring 2008 to complete.

Subject to further funding being obtained, the implementation of the project should hopefully start in Summer 2008, leading to commissioning by the end of 2008.

2. Recent Developments

back to top

3. Local concerns answered

  1. Low residual flow in the Angiddy. Various figures have been quoted, which are unsubstantiated. The actual flow rate in the Angiddy is being monitored and will continue to be over the coming months. TAP will not be allowed to reduce the flow level to below the natural minimum level.
  2. Furnace Pond will silt up. The current procedure is to open the sluice gates in the Furnace Pond for several days in February each year in order to flush out the silt. TAP will maintain this schedule. For the days in question there will be no power generated as full flow will be diverted into the Angiddy.
  3. Scarring the landscape in the valley. The pipe will be buried under existing permissive paths and footpaths. There will be some damage to the vegetation alongside these paths during installation, and a small number of trees will be felled. Landscaping will be carried out, the paths re-made and within 12 months the route of the pipe will not be visible. At the input end there will be a stainless steel collection / filter box at the base of the Beaufort Pond dam. This will be approximately 1 cubic metre in size and as it is at river level will not be very visible. At the bottom end of the pipe there will be a small turbine house situated away from the road and concealed by trees. It will be approximately the size of a single vehicle garage and built of dark natural materials so again will be of low visible impact. Connections to the National Grid will be by underground cable.
  4. How is the profit calculated? All the power generated will be sold to the National Grid. This will provide the income from the project. On the expense side, TAP will have to pay Corporation Tax at 20%, an insurance premium, a small cost to cover education initiatives for local schools, and to allocate a sum for annual maintenance. There will be no staff costs as the project will be run entirely by volunteers. Income minus these expenses will be the profit.
  5. How will the profit be distributed? A committee, made up of representatives of the various clubs and organisations which exist within the Tintern Community, will be set up. TAP will donate the annual profit to this committee. The committee will be empowered to decide how to spend the money. TAP will not participate in this process but will fix the guide lines. I.e. Money must be spent within the Tintern Community; Projects should improve local amenities; or support the various clubs, groups and organisations; or support renewable energy projects.

back to top

4. Motivation behind the project

back to top